Interpret an envelope assembly's R-value or U-factor against IECC 2024 (or ASHRAE 90.1-2022) by climate zone. Output is an inline pass/fail interpretation with prescriptive table reference, performance-path implication, and ASHRAE alternative. For full energy modeling or COMcheck / REScheck documentation, use the energy-compliance skill.
Input you need
Before interpreting, gather:
- Assembly — describe the layered build:
- Wall —
mass,metal-framed,wood-framed,framed + continuous insulation (CI). - Roof —
insulation entirely above deck,metal building,attic and other. - Floor —
mass,steel-joist,wood-framed. - Slab on grade — perimeter R-value and depth (
F-factorperIECC 2024 Table C402.1.4). - Below-grade wall — CI rating and depth.
- Fenestration — U-factor, SHGC, VT, frame type (
vinyl,aluminum thermally broken,fiberglass).
- Wall —
- R-value or U-factor proposed — provide both if known. R-values lead in NA practice; U-factors only for fenestration and the U-factor alternative path in
IECC 2024 §C402.1.4. - Climate zone (CZ) —
ASHRAE 169/IECC 2024 Ch. 3designation:1A,2A,2B,3A–3C,4A–4C,5A–5C,6A–6B,7,8. Examples:NYC CZ 4A,LA CZ 3B,Toronto CZ 6A,Houston CZ 2A,Phoenix CZ 2B,Chicago CZ 5A,Minneapolis CZ 6A,Miami CZ 1A. - Project type / occupancy —
commercial(IECC 2024 Ch. C) vsresidential(IECC 2024 Ch. R). For commercial, the R-occupancy distinction matters:R-2group counts as commercial underIECC §C402unless individually metered low-rise. - Path —
prescriptive(table compliance),performance(whole-building energy modeling perIECC §C407or§R405),ECB(Energy Cost Budget perASHRAE 90.1-2022 §11), oroutcome-based. Prescriptive is the most common SD/DD gut-check path. - AHJ —
NYC DOB(NYC Energy Conservation Code +Local Law 97carbon overlay),LADBS(CA Title 24 Part 6),DSA(CA K-12),CA HCAI(CA hospitals),Toronto Building(OBC SB-10),Boston ISD(Stretch Energy Code).CA Title 24 Part 6is stricter than IECC on many lines. - Specific question — Examples: "Is
R-30batts +R-5 CIenough for a 2x6 wall inCZ 4A?", "DoesU-0.32fenestration pass forCZ 5Acommercial?", "What R-value for slab perimeter inToronto CZ 6A?"
If the climate zone is missing, name the project city — pair with climate-zone-mapper for authoritative CZ assignment.
Output structure
# Explain U-value — [Assembly, CZ, R-value]
**Assembly:** [2x6 wood-framed wall + R-5 CI / Roof insulation entirely above deck / Vinyl fenestration]
**Proposed:** [R-30 cavity + R-5 CI / U-0.32 / SHGC 0.40]
**Climate zone:** [CZ 4A — NYC]
**Project type:** [commercial — IECC 2024 §C402 / residential — IECC 2024 §R402]
**Path:** [prescriptive / performance / ECB / outcome-based]
**Question:** [the user's specific question]
---
## What IECC 2024 requires (literal)
> [Verbatim values from `IECC 2024 Table C402.1.3` (R-value alternative for above-grade walls), `Table C402.1.4` (U-factor alternative), `Table C402.4` (fenestration), `Table R402.1.2` (residential R-value), `Table R402.1.3` (residential U-factor).]
(IECC 2024 Table C402.1.3, climate zone [X])
## Pass / fail
- **R-value path** — [Compare proposed against `Table C402.1.3` minimum.]
- **U-factor alternative** — [Per `IECC 2024 §C402.1.4`, the assembly may comply via U-factor — compare against `Table C402.1.4`.]
- **Performance path** — [If prescriptive fails, the assembly may pass under whole-building modeling per `IECC 2024 §C407`. Flag without claiming the model passes — modeling is required.]
## ASHRAE 90.1-2022 alternative
- [Bullet — `IECC 2024 §C401.2` permits `ASHRAE 90.1-2022` as an alternative path. Cite the equivalent `ASHRAE 90.1-2022 §5.5` table by CZ for cross-check.]
## Jurisdictional flags
- **`CA Title 24 Part 6`** — stricter than IECC on most lines; confirm via `DSA` / `CA HCAI` / `LADBS` reviewer.
- **`NYC DOB` + `Local Law 97`** — layers carbon-intensity targets on top of envelope compliance; envelope-only gut-checks are insufficient for `Local Law 97` reporting.
- **`Toronto Building` (`OBC SB-10`)** — references `ASHRAE 90.1` with provincial amendments; verify project-specific compliance with `Toronto Building` plan reviewer.
- **`NYC SCA`** — schools layer NYC CECC on top of NYC Energy Code; coordinate with `NYC SCA` design review.
- **`Boston ISD`** — `Stretch Energy Code` raises prescriptive minimums above base IECC.
- If no AHJ-specific amendment is known, state explicitly. Do not guess.
## Cross-references
- [Bullet — `IECC 2024 Table C402.1.3` (R-value), `Table C402.1.4` (U-factor), `Table C402.4` (fenestration), `Table C402.5` (air leakage).]
- [Bullet — `ASHRAE 90.1-2022 §5.5` (CZ-specific envelope criteria), `App. A` (assembly U-factor calculations).]
- [Bullet — `IECC 2024 §C406` (additional efficiency packages — required for commercial in the 2024 cycle).]
## Caveats
- Effective R-value depends on framing factor (~23% for 2x6 @ 16 in o.c.) and thermal bridging through fasteners. Cavity R-value alone overstates assembly performance — use `Tables C402.1.3 / C402.1.4` which build the framing factor in, or compute assembly U-factor per `ASHRAE 90.1-2022 App. A`.
- Prescriptive compliance is a floor, not a ceiling. `NYC Local Law 97`, `CA Title 24 Part 6`, and outcome-based codes (`Boston Stretch Code`, `Vancouver Zero Emissions Building Plan`) often require performance modeling.
- This is a gut-check, not stamped energy compliance. `COMcheck` / `REScheck` or whole-building energy modeling is required for permit submission.
- For full energy compliance documentation, use the `energy-compliance` skill.
NA AEC conventions (enforce)
- English only. No Hangul anywhere.
- R-values lead, U-factors second. Never lead with metric U-values (
W/m²K). When U-factor is needed (fenestration, U-factor alternative), cite IECCU-X.XXform (e.g.,U-0.32). - Climate zones —
ASHRAE 169/IECC 2024 Ch. 3:1A…8. Always specify with letter suffix where present. - Codes cited —
IECC 2024(commercial Ch. C, residential Ch. R),ASHRAE 90.1-2022,ASHRAE 90.2-2018,NBC 2020 Div. B Sec. 9.36,OBC SB-10,CA Title 24 Part 6. NeverKBC,KS,EN,BS,JIS,DIN— out of catalog scope. - AHJs —
NYC DOB,LADBS,DSA,CA HCAI,Toronto Building,Boston ISD,Chicago DOB. Neverthe AHJ,the city, orlocal authoritygenerically. - Roles —
Architect of Record (AOR),MEP Engineer,Energy Modeler,Commissioning Authority (CxA),LEED AP. Never useDirectoras a project role. - Imperial-first units; SHGC and VT are dimensionless; framing spacing in
in o.c.. - Floor labels —
L3,Level 3,3rd floor. Never3F.
Constraints
- Do not invent IECC table values from memory. Either cite the verbatim table value (preferred — pull via
arch-ragif the IECC PDF is indexed) or state the prescriptive minimum is to be verified against the table. - Do not collapse cavity R-value + CI R-value linearly. Use IECC's tabular U-factor alternative or assembly U-factor calculations per
ASHRAE 90.1-2022 App. A— framing factor matters. - Distinguish prescriptive vs performance vs ECB paths. A prescriptive fail is not a project fail if performance modeling is in scope.
- Coexists with
energy-complianceskill (fullCOMcheck/REScheck/ model). For permit-ready documentation, redirect. - Markdown only. No Word / PDF output, no
aec-doc-gendependency.
Workflow
- Echo back: assembly, proposed R / U, climate zone, project type, path, question. One line.
- If climate zone is missing, infer from city using
climate-zone-mapperor ask. CA cities default toTitle 24 Part 6review. - If the proposed value is cavity R-value only and the assembly is framed, flag the framing-factor caveat before citing pass/fail.
- Produce the response in one shot.
- Surface next-step compliance work explicitly (e.g., "Prescriptive fails by 2 R-values → engage MEP Engineer for performance modeling per
IECC 2024 §C407, or upgrade toR-30 + R-7.5 CIto clearTable C402.1.3").